Hi,
As per the Documentation, there should be an option to set a Specific date for New Code in the project administration. However, only Previous version and Number of days can be choosen.
Is there anyhing I missing?
Thanks
– Vazul
Hi,
As per the Documentation, there should be an option to set a Specific date for New Code in the project administration. However, only Previous version and Number of days can be choosen.
Is there anyhing I missing?
Thanks
– Vazul
Hi Vazul,
Welcome to the community!
I think the ‘Specific date’ option is like the ‘Specific version’ option, in that it can only be set via the APIs.
I’m going to flag this for the documentation team to make that clearer.
HTH,
Ann
Thanks for the feedback, I’ve updated the docs to point out this option is only available via the API