Consider Below Data :
Today’s Date : April 07, 2025
New Code Setting : Last 180 Days
Project A :
Last Analysis Date : April 07,2025
Available Analysis Dates : Oct 11,2024 & Oct 04,2024
Project B :
Last Analysis Date : April 05,2025
Available Analysis Dates : Oct 12, 2024 & Oct 04, 2024
With the above Data, i would like to confirm how New Code Period Start Date is determined for the above projects.
Question 1 : Since the New Code settings is Last 180 Days, do we need to minus 180 days from today’s date or Last Analysis Date of a project ?
For project B, Today’s Date - 180 Days (or) April 05, 2025 (Last Analysis Date) - 180 Days. Which one is followed by SQ?
Question 2 : After Subtracting the 180 days from the respective date, if analysis is not available exactly on that date, how new code start date is determined.
For Project A, April 7, 2025 - 180 Days = Oct 9,2024 for which we don’t have analysis data. In this case, how New Code Period Start Date is determined out of below cases
CASE - 1 : Next Immediate Analysis after Oct 9,2024
CASE - 2 : Immediate Previous Analysis before Oct 9,2024
CASE - 3 : Analysis Date whichever is closer Oct 9, 2024
Out of above three cases, which one is considered.